Home / Asia / Indonesia / Keramasan Asta power station

Keramasan Asta power station

Gas power plant in Sumatra, Indonesia. Approximate location -3.030261, 104.741981.

GasSumatraIndonesiaCCGT · HRSGMothballed

Keramasan Asta power station is a 145 MW gas power station in Sumatra, Indonesia. It is operated by PT Asta Keramasan Energi [100%]. Based on its capacity (estimated), it can supply roughly 163k homes (estimated). It ranks #219 of 401 Indonesia power plants by installed capacity. Commissioned in 2010, it is around 16 years old — relatively modern. In context, gas supplies about 18.5% of Indonesia's electricity; the national grid averages 680 gCO₂/kWh (18.1% low-carbon) (2024).

145MW installed capacity
1HRSG unit(s)
163,311homes powered (est.)
2010commissioned (~16 yrs)

Plant data: WRI Global Power Plant Database (CC BY 4.0), id GOGPT_keramasanasta_indone.

Data status

Known data

FacilityKeramasan Asta power station GEM-GOGPT
CountryIndonesia · Sumatra GEM-GOGPT
Coordinates-3.030261, 104.741981 GEM-GOGPT
FuelGas GEM-GOGPT
MW installed capacity145 MW GEM GOGPT; source record
OwnerPT Asta Keramasan Energi [100%] GEM-GOGPT
Commissioned2010 GEM-GOGPT
TechnologyCCGT · HRSG GEM-GOGPT

Calculated from dataset

CO₂ emissions228,636 t CO₂·a⁻¹ calculated
Capacity rank in country#219 / 401 calculated
Fuel-specific rank in country#73 / 138 calculated
Capacity vs country/fuel peers0.97× · 150 MW · n=138 calculated
Homes-powered equivalent163,311 calculated
Environmental severityC4 · 42/100 derived from coordinates

Not available

GWh reported / yrNot available not in dataset

Known, modelled and calculated values are kept separate. Missing fields are shown as unavailable.

Data provenance

The capacity and fuel fields on this page are source-record values from the upstream open dataset. They are useful for identification and ranking, but they have not been upgraded to a 2026 registry/GEM-location verified value.

capacity: GEM GOGPT; fuel: GEM GOGPT

In context: how this plant compares

At 145 MW, Keramasan Asta power station is around the median gas plant in Indonesia (150 MW). Technically it is described as CCGT; combined-cycle with a heat-recovery steam generator (HRSG). Its current lifecycle status is “Mothballed” — so it is not yet, or no longer, generating at full output. Gas plants burn natural gas either in open-cycle turbines for fast peaking, or in combined-cycle units that recover exhaust heat in an HRSG to reach roughly 55–62% efficiency — the cleanest-burning fossil option.

Capacity comparison computed from the WRI Global Power Plant Database; fuel-type context is general engineering background.

Capacity vs largest gas plants in Indonesia

Batubara power station: 4,800 MW5kBatubara p…Sujiawumei LNG power station: 2,400 MW2kSujiawumei…PLTGU Jawa-1 power station: 1,760 MW2kPLTGU Jawa…PLTGU Gresik: 1,579 MW2kPLTGU Gres…PLTGU Priok Block 1 2: 1,180 MW1kPLTGU Prio…PLTGU Tambak Lorok: 1,034 MW1kPLTGU Tamb…Jawa-4 power station: 1,000 MW1kJawa-4 pow…Jawa-5 power station: 1,000 MW1kJawa-5 pow…

Installed capacity (MW), WRI Global Power Plant Database (CC BY 4.0).

Owner

Operated by PT Asta Keramasan Energi [100%].

Climate zone & how it works

This gas plant burns natural gas in a turbine — often in a combined-cycle setup — to generate electricity. It sits in a tropical rainforest climate (Köppen Af) — Southern Hemisphere, latitude 3.0°S — which shapes how much energy it can produce and how its output varies through the year.

~26°Ctypical annual mean
~27°Ctypical warm-season mean
Tropical rainforest: hot and humid year-round with little seasonal variation

Climate zone & typical temperatures: Köppen-Geiger world climate classification (Kottek et al. 2006, 0.5° grid).

Site climate & environmental severity

For a plant’s outdoor hardware — heat-recovery steam generators (HRSG), expansion joints, valves, flanges and their insulation — the local climate sets how fast unprotected steel and coatings degrade. This site sits in a corrosive environment (estimated ISO 9223 class C4 — High), with humidity / wetness the leading environmental stress.

C4ISO 9223 corrosivity (indicative)
42/100environmental-severity index
1.1°Cseasonal temperature swing
117 kmdistance to coast

Higher environmental severity is exactly where protective removable insulation pays back most: a sheltered micro-climate slows corrosion, UV and thermal-cycling damage and extends outdoor hardware service life. This is an indicative site-climate context — not a condition assessment of any specific plant or operator.

Indicative estimate via the ISO 9223:2012 informative method (atmospheric corrosivity from temperature, time-of-wetness and airborne salinity), using WorldClim climate normals, the Köppen-Geiger class and coast distance. Indicative, not a measured corrosion rate.

How it compares & nearby plants

The #73 largest gas power plant of 138 in Indonesia by capacity.

Indonesia has 138 gas power plants in this dataset, together about 44,657 MW of capacity.

Nearby power plants

Location

Coordinates -3.030261, 104.741981 from WRI Global Power Plant Database (CC BY 4.0). View on OpenStreetMap.

Frequently asked questions

What type of power plant is Keramasan Asta power station?

Keramasan Asta power station is a 145 MW gas power plant in Sumatra, Indonesia, commissioned in 2010.

How many homes can Keramasan Asta power station power?

Its output is enough to supply roughly 163,311 homes (estimated).

Who operates Keramasan Asta power station?

Keramasan Asta power station is operated by PT Asta Keramasan Energi [100%].

Built from open public data; no personal information. Operate this site? Request a correction or removal.