The order is based on Climate TRACE modelled estimates for 2023 after repeated placeholder values are removed.
This is a ranking within the stated modelled dataset. It is not a verified emissions league table, a current inventory or a liability ranking.
| Rank | Facility | Country | Modelled sector | Estimated t CO2, 2023 |
|---|---|---|---|---|
| 1 | Jinfeng Cement Plant | China | cement | 6,703,459 |
| 2 | Sungshin Cement Danyang Cement Plant | South Korea | cement | 6,146,734 |
| 3 | Obajana Cement Plant | Nigeria | cement | 5,910,670 |
| 4 | Lucky Cement Pezu Cement Plant | Pakistan | cement | 5,508,813 |
| 5 | Semen Gresik Tuban Cement Plant | Indonesia | cement | 5,147,322 |
| 6 | TPI Polene Mittaphap Cement Plant | Thailand | cement | 4,529,439 |
| 7 | Anhui Panjing Cement Co. Cement Plant | China | cement | 4,351,463 |
| 8 | National Cement New Beni Suef Cement Plant | Egypt | cement | 4,345,506 |
| 9 | Sokoto Cement Plant | Nigeria | cement | 4,320,860 |
| 10 | China Resources Cement (Fengkai) Ltd Cement Plant | China | cement | 4,250,669 |
| 11 | Sichuan Xingchuancheng Cement Co.,Ltd. Cement Plant | China | cement | 4,249,812 |
| 12 | Indocement Tunggal Prakarsa Citeureup Cement Plant | Indonesia | cement | 4,236,315 |
| 13 | Kesoram Industries Gulbarga Cement Plant | India | cement | 4,165,911 |
| 14 | UltraTech Anantapuram Cement Plant | India | cement | 4,123,869 |
| 15 | Lafarge Attaka Cement Plant | Egypt | cement | 4,073,231 |
| 16 | Sichuan Easun Cement Group Co. Cement Plant | China | cement | 4,051,303 |
| 17 | Dongfang Hope Chongqing Cement Co.,Ltd. Cement Plant | China | cement | 3,929,237 |
| 18 | Eagle Bulacan Cement Plant | Philippines | cement | 3,801,584 |
| 19 | Semen Tonasa Cement Plant | Indonesia | cement | 3,795,567 |
| 20 | Shandong Shenfeng Cement Group Co. Cement Plant | China | cement | 3,700,459 |
Use measured surface area, temperature and operating hours to calculate heat loss from boilers, kilns, heat exchangers, valves and pipework. Inzonex supplies removable modular insulation for equipment that requires maintenance access.
Do not add a calculated reduction to an emissions report until the reporting boundary, factor, implementation date and verification method have been approved.