Home / Asia / Malaysia / Petrochemical plants / Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor

Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor — Malaysia

Petrochemical in Malaysia. Approximate location 1.37623, 104.16782.

PetrochemicalMalaysiaCO₂ estimate (modelled)

Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor is a petrochemical plant in Malaysia. Its listed capacity is 1,290,000 t of ethylene. Petrochemical plants crack hydrocarbons at very high temperatures to produce ethylene, propylene and other building-block chemicals — one of the most heat-intensive industrial processes. It is operated by Saudi Arabian Oil Co. By capacity it ranks #1 among 3 petrochemical plants in Malaysia. It emits about 2,645,670 t CO₂e a year from Climate TRACE. That is 6.2% of the CO₂e from the 39 facilities in Malaysia that have an emissions figure in IndustryAtlas. Its CO₂ per unit of capacity is 57% above the national median for this sector.

1,290,000t of ethylene
2,645,670t CO₂e / yr (Climate TRACE)
#3CO₂ rank in Malaysia
2.05t CO₂ per capacity unit

Facility data: Climate TRACE v6 (asset-level capacity & CO₂e, CC BY 4.0), id ct-731963.

Data status

Known source data

FacilityPengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor Climate TRACE
CountryMalaysia Climate TRACE
Coordinates1.37623, 104.16782 Climate TRACE
Sector / subsectorpetrochemical-steam-cracking Climate TRACE
Reported capacity1,290,000 t of ethylene Climate TRACE
Owner / operatorSaudi Arabian Oil Co Climate TRACE
Modelled CO₂e2,645,670 t/yr Climate TRACE

Calculated from the dataset

Malaysia rank#3 of 39 · top 7.7% calculated
Global petrochemical-steam-cracking rank#18 of 218 · top 8.3% calculated
Climate contextderived from coordinates calculated

Not available

Fuel typeNot available not in dataset
Thermal capacity (MW)Not available not in dataset

Source data, measured cross-checks and calculated values are kept separate. No confidence percentage is invented.

Similar facilities by modelled emissions

Same Climate TRACE subsector; closest non-placeholder modelled CO₂e values. Russia and Belarus excluded.

Operating power plants within 50 km

PowerAtlas operating assets, ordered by great-circle distance from published coordinates.

In context: how this facility compares

At 1,290,000 t of ethylene, Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor is around the median petrochemical plant in Malaysia (1,040,000 t of ethylene). Subsector: petrochemical-steam-cracking. As petrochemical plant, it requires high process heat (typically 300–800°C) for its core industrial operations, supplied by boilers, furnaces or direct combustion. Petrochemical plants crack hydrocarbons at very high temperatures to produce ethylene, propylene and other building-block chemicals — one of the most heat-intensive industrial processes.

Capacity & CO₂-intensity comparison computed from Climate TRACE industrial facilities data; sector role based on engineering reference.

What 2,645,670 t CO₂e a year looks like

This facility's estimated annual CO₂e (Climate TRACE, modelled) in everyday equivalents from the US EPA Greenhouse Gas Equivalencies calculator:

6.2 millionbarrels of crude oil burned
617kgasoline cars driven for a year
790wind turbines running for a year

Equivalencies: US EPA Greenhouse Gas Equivalencies. Emissions: Climate TRACE.

Carbon cost and Scope 1 emissions

At its reported 2.6M t CO₂e/yr (Scope 1), Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor carries no domestic carbon price, and its products are not CBAM-covered goods, so there is no border-carbon liability. At the EU ETS reference price (€75/t) the emissions carry an indicative carbon value of €199M/yr.

2.6M t CO₂e / yrScope 1 emissions
€199M/yrindicative carbon value (not a CBAM liability)

Carbon price: EU CBAM €75/t · EU ETS €85/t, September 10, 2026, refreshed live via Carbon Hub. CO₂: Climate TRACE. Indicative carbon value, not the cash bill — free allocation applies; not compliance advice.

Capacity vs largest petrochemical plants in Malaysia

Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor: 1,290,000 t of ethylene1.3MPengerang …Petronas Chemicals Ethylene, Sdn. Bhd. Kertih: 1,040,000 t of ethylene1.0MPetronas C…Lotte Chemical Titan, Sdn. Bhd. Pasir Gudang, Johor: 807,000 t of ethylene807kLotte Chem…

Listed capacity (t of ethylene), Climate TRACE v6 (asset-level capacity & CO₂e, CC BY 4.0).

Local climate

Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor sits in a tropical rainforest climate zone (Köppen Af), at 1.4°N in the northern hemisphere.

~26°Ctypical annual mean
~27°Ctypical warm-season
Tropical rainforest: hot and humid year-round with little seasonal variation

Köppen zone: Köppen-Geiger world climate classification (Kottek et al. 2006, 0.5° grid).

Site climate & environmental severity

This site sits in an aggressive, high-corrosion environment (estimated ISO 9223 class C5 — Very high), with marine salt corrosion the leading environmental stress.

C5ISO 9223 corrosivity (indicative)
49/100environmental-severity index
1.5°Cseasonal temperature swing
44 kmdistance to coast
Very highCUI risk tier

In this site’s local climate, a bare 150 °C surface sheds about 1230 W/m² to ambient — roughly 0.95× the loss at a 20 °C reference. Reference-surface calculation at a 150 °C surface from WorldClim climate normals (ASTM C680 / ISO 12241) — an indicative per-climate comparison, not a measurement of this site’s specific equipment. Open method dataset: DOI 10.5281/zenodo.20787408 (CC BY 4.0).

Indicative estimate via the ISO 9223:2012 informative method (atmospheric corrosivity from temperature, time-of-wetness and airborne salinity), using WorldClim climate normals, the Köppen-Geiger class and coast distance. Indicative, not a measured corrosion rate.

How it compares & nearby sites

The #1 largest of 3 petrochemical plants in Malaysia by listed capacity (Climate TRACE).

Nearby industrial sites

Location

Coordinates 1.37623, 104.16782. View on OpenStreetMap.

Frequently asked questions

What type of facility is Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor?

Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor is a petrochemical plant in Malaysia. Petrochemical plants crack hydrocarbons at very high temperatures to produce ethylene, propylene and other building-block chemicals — one of the most heat-intensive industrial processes.

What capacity is listed for Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor?

The open dataset lists 1,290,000 t of ethylene of capacity for Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor.

How much CO₂ does Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor emit?

The page uses about 2,645,670 t CO₂e/year from the open dataset It ranks #3 among facilities in Malaysia by estimated CO₂.

Where is Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor located?

Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor is in Malaysia at approximately 1.37623, 104.16782.

Who operates Pengerang Refinery and Petrochemical Integrated Development (RAPID), Pengerang, Johor?

The operator recorded in the open dataset is Saudi Arabian Oil Co.

Built from open public data; no personal information. Operate this site? Request a correction or removal.