Beckum-Kollenbach Cement Plant is a cement plant in Germany. Its listed capacity is 1,250,000 t of cement. Cement plants heat limestone to 1,400°C in rotary kilns — one of the hottest industrial processes — and must control temperature precisely across the entire kiln length. It is operated by Holcim (Deutschland) GmbH. By capacity it ranks #4 among 12 cement plants in Germany. It emits about 162,847 t CO₂e a year from Climate TRACE. That is 0.14% of the CO₂e from the 118 facilities in Germany that have an emissions figure in IndustryAtlas. Its CO₂ per unit of capacity is 64% below the national median for this sector.

1,250,000t of cement
162,847t CO₂e / yr (Climate TRACE)
#79CO₂ rank in Germany
0.13t CO₂ per capacity unit

Facility data: Climate TRACE v6 (asset-level capacity & CO₂e, CC BY 4.0), id ct-32438328.

Data status

Known source data

FacilityBeckum-Kollenbach Cement Plant Climate TRACE
CountryGermany Climate TRACE
Coordinates51.76546, 8.05631 Climate TRACE
Sector / subsectorcement Climate TRACE
Reported capacity1,250,000 t of cement Climate TRACE
Owner / operatorHolcim (Deutschland) GmbH Climate TRACE
Modelled CO₂e162,847 t/yr Climate TRACE
Measured CO₂ cross-check495,048 t/yr measured cross-check · EUTL 2023

Calculated from the dataset

Germany rank#79 of 118 · top 66.9% calculated
Global cement rank#1924 of 2113 · top 91.1% calculated
Climate contextderived from coordinates calculated

Not available

Fuel typeNot available not in dataset
Thermal capacity (MW)Not available not in dataset

Source data, measured cross-checks and calculated values are kept separate. No confidence percentage is invented.

Similar facilities by modelled emissions

Same Climate TRACE subsector; closest non-placeholder modelled CO₂e values. Russia and Belarus excluded.

Operating power plants within 50 km

PowerAtlas operating assets, ordered by great-circle distance from published coordinates.

In context: how this facility compares

At 1,250,000 t of cement, Beckum-Kollenbach Cement Plant is well above the median cement plant in Germany (950,000 t of cement). Subsector: cement. As cement plant, it requires high process heat (typically 800–1400°C) for its core industrial operations, supplied by boilers, furnaces or direct combustion. Cement plants heat limestone to 1,400°C in rotary kilns — one of the hottest industrial processes — and must control temperature precisely across the entire kiln length.

Capacity & CO₂-intensity comparison computed from Climate TRACE industrial facilities data; sector role based on engineering reference.

What 162,847 t CO₂e a year looks like

This facility's estimated annual CO₂e (Climate TRACE, modelled) in everyday equivalents from the US EPA Greenhouse Gas Equivalencies calculator:

903railcars of coal burned
34khomes' electricity use for a year
163kacres of US forest absorbing CO₂ for a year

Equivalencies: US EPA Greenhouse Gas Equivalencies. Emissions: Climate TRACE.

Carbon cost and Scope 1 emissions

At its reported 163k t CO₂e/yr (Scope 1), Beckum-Kollenbach Cement Plant carries €13.9M/yr of carbon at the full EU ETS price (€85/t CO₂). Free allocation phases out to 2034 (Reg. (EU) 2023/956), so today's bill is lower and rising toward this full-price figure.

Measured CO₂: 495k t/yr — verified EUTL (reporting year 2023) (204% above the modelled estimate). Modelled estimate 163k t/yr (Climate TRACE), high-confidence match, cross-checked via the measured-vs-modelled dataset (n=711).

163k t CO₂e / yrScope 1 emissions
€13.9M/yrcarbon value · full EU ETS price

Carbon price: EU ETS €85/t · EU ETS €85/t, September 10, 2026, refreshed live via Carbon Hub. CO₂: measured (EUTL RY2023), cross-checked vs Climate TRACE. Indicative carbon value, not the cash bill — free allocation applies; not compliance advice.

Capacity vs largest cement plants in Germany

Rudersdorf Cement Plant: 1,900,000 t of cement1.9MRudersdorf…Lengerich Cement Plant: 1,770,000 t of cement1.8MLengerich …Lagerdorf Cement Plant: 1,310,000 t of cement1.3MLagerdorf …Beckum-Kollenbach Cement Plant: 1,250,000 t of cement1.2MBeckum-Kol…Rohrdorf Cement Plant: 970,000 t of cement970kRohrdorf C…Amoneburg Cement Plant: 950,000 t of cement950kAmoneburg …Heidelberg Geseke Cement Plant: 900,000 t of cement900kHeidelberg…Bernburg Cement Plant: 860,000 t of cement860kBernburg C…

Listed capacity (t of cement), Climate TRACE v6 (asset-level capacity & CO₂e, CC BY 4.0).

Local climate

Beckum-Kollenbach Cement Plant sits in a temperate oceanic climate zone (Köppen Cfb), at 51.8°N in the northern hemisphere.

~11°Ctypical annual mean
~18°Ctypical warm-season
Temperate oceanic: four distinct seasons — cold winters and warm summers

Köppen zone: Köppen-Geiger world climate classification (Kottek et al. 2006, 0.5° grid).

Site climate & environmental severity

This site sits in a mild atmospheric environment (estimated ISO 9223 class C2 — Low), with humidity / wetness the leading environmental stress.

C2ISO 9223 corrosivity (indicative)
23/100environmental-severity index
15.5°Cseasonal temperature swing
171 kmdistance to coast
LowCUI risk tier

In this site’s local climate, a bare 150 °C surface sheds about 1409 W/m² to ambient — roughly 1.08× the loss at a 20 °C reference. Reference-surface calculation at a 150 °C surface from WorldClim climate normals (ASTM C680 / ISO 12241) — an indicative per-climate comparison, not a measurement of this site’s specific equipment. Open method dataset: DOI 10.5281/zenodo.20787408 (CC BY 4.0).

Indicative estimate via the ISO 9223:2012 informative method (atmospheric corrosivity from temperature, time-of-wetness and airborne salinity), using WorldClim climate normals, the Köppen-Geiger class and coast distance. Indicative, not a measured corrosion rate.

How it compares & nearby sites

The #4 largest of 12 cement plants in Germany by listed capacity (Climate TRACE).

Nearby industrial sites

Location

Coordinates 51.76546, 8.05631. View on OpenStreetMap.

Frequently asked questions

What type of facility is Beckum-Kollenbach Cement Plant?

Beckum-Kollenbach Cement Plant is a cement plant in Germany. Cement plants heat limestone to 1,400°C in rotary kilns — one of the hottest industrial processes — and must control temperature precisely across the entire kiln length.

What capacity is listed for Beckum-Kollenbach Cement Plant?

The open dataset lists 1,250,000 t of cement of capacity for Beckum-Kollenbach Cement Plant.

How much CO₂ does Beckum-Kollenbach Cement Plant emit?

The page uses about 162,847 t CO₂e/year from the open dataset It ranks #79 among facilities in Germany by estimated CO₂.

Where is Beckum-Kollenbach Cement Plant located?

Beckum-Kollenbach Cement Plant is in Germany at approximately 51.76546, 8.05631.

Who operates Beckum-Kollenbach Cement Plant?

The operator recorded in the open dataset is Holcim (Deutschland) GmbH.

Built from open public data; no personal information. Operate this site? Request a correction or removal.