| # | Facility | t of cement | t CO₂e/yr |
|---|---|---|---|
| 1 | Lafarge Settat Cement Plant 2 | 3,000,000 | 1,508,077 |
| 2 | Tetouan Cement Plant | 2,500,000 | 240,708 |
| 3 | Imi Mqourn Cement Plant | 2,200,000 | 454,191 |
| 4 | Meknes Cement Plant | 1,750,000 | 904,156 |
| 5 | Lafarge Settat Cement Plant 1 | 1,700,000 | 519,378 |
| 6 | Ouled Ghanem Cement Plant | 1,600,000 | 583,482 |
| 7 | Lafarge Taroudant Cement Plant | 1,600,000 | 504,461 |
| 8 | Dir El Ksiba Cement Plant | 1,600,000 | 423,115 |
| 9 | Loulad Cement Plant | 1,600,000 | 305,680 |
| 10 | Mzouda Cement Plant | 1,400,000 | 528,289 |
| 11 | Temara Cement Plant | 1,400,000 | 459,142 |
| 12 | Mghizrate Cement Plant | 1,300,000 | 325,042 |
| 13 | Ain Chkef Cement Plant | 1,200,000 | 363,999 |
| 14 | Had Hrara Cement Plant | 1,000,000 | 478,926 |
Climate TRACE v6 (asset-level capacity & CO₂e, CC BY 4.0).